The Office of Surface Mining uses this Financial Assistance Manual to show how OSM and its grantees manage Federal grants. This chapter tells how to close out a completed regulatory grant.

CHAPTER 5-70R
REGULATORY GRANT PROGRAM
CLOSEOUT POLICY AND PROCEDURES

5-70R-00 PURPOSE

This chapter provides OSM policy and procedures for the closeout of completed regulatory grants.

5-70R-10 OSM POLICY

  1. Grants are normally closed out no later than 180 calendar days after the end of the performance period. The first 90 days are allotted for grantees to provide documentation to OSM; the remaining ninety days are allotted for OSM to complete the closeout process.

  2. A grant shall not be closed (1) if the grant is in litigation or under appeal; (2) if, in the event the grant has been terminated, all termination actions have not yet been accomplished; (3) until all allowable, allocable, and reasonable costs have been paid and all excess funds deobligated; and (4) until the OSM office administering the grant certifies in writing that all the procedures set forth in this chapter have been accomplished.

  3. The closeout of a grant does not affect the retention period for, or Federal rights of access to, grant records, nor the recipient's responsibility with respect to property or equipment purchased with grant assistance. Grants may be closed without audit; however, a subsequent audit may identify allowable or questioned costs that may require additional administrative action.

5-70R-20 CLOSEOUT REQUIREMENTS

  1. General. Recipients shall submit one signed original and no more than two copies of documentation to close out completed budget/cost categories and grants.

  2. Closeout Package - Regulatory Grant . A complete closeout package for a nonconstruction regulatory grant consists of:

    Document Name Form No.
    Transmittal Letter

    Final Performance Report

    Final Financial Status Report

    Property Report (Grantee Purchased)

    Property Report (Federally-Owned)

    --

    OSM 51

    SF 269 or 269A

    OSM 60

    OSM 60

  3. Guidance for preparing a complete closeout package for a regulatory grant is provided at Exhibit X5-70R-1.

5-70R-30 INTERNAL PROCEDURES

  1. Upon receipt of the closeout information, the designated OSM office shall review the documentation to determine if the recipient has submitted a complete and acceptable closeout package, as outlined in Part A of the Grant/Cooperative Agreement Closeout Checklist, OSM 61R (Exhibit X5-70R-2). If the closeout package is acceptable, within 60 days after receipt of the complete closeout package, the OSM office shall complete the actions listed in Part B of the OSM 61B (Exhibit X5-70B-2) . If the closeout package is unacceptable, OSM may return the documents to the recipient with an explanation of what must be done to make the package acceptable, request additional information from the recipient, or resolve the problems through telephone conversations.

  2. Within 60 days of receipt of a complete closeout package from the grantee, the assigned OSM regional/field office shall complete all actions outlined in Part B of the OSM 61R. The designated office then shall sign the final OSM 52 and forward it to DFM to officially close the grant.

  3. Within 5 days of receipt of a completed closeout package, DFM shall complete all required actions to record the closeout of the grant and, if required, deobligate funds.

  4. The designated OSM office shall notify the recipient of OSM's actions and of the record retention requirements.

5-70R-40 EXTENSION OF FINAL REPORT DUE DATES

  1. The recipient shall make every reasonable effort to close the grant no later than 90 calendar days following its expiration. The designated OSM office, may at its discretion, extend the due date for the final financial/performance reports upon receipt of written justification from the recipient. Approval of a request to extend the due date is contingent upon the receipt, no later than 30 calendar days after the end of the performance period, of an interim SF 269 or SF 269A and OSM 51.

    If a closeout cannot be submitted within 90 days, an interim report must be submitted consisting of a financial report and narrative statement.

  2. The responsible OSM office shall transmit to DFM one copy of the signed OSM 52 showing the revised closeout date.


EXHIBIT X5-70R-1

GUIDANCE ON PREPARING DOCUMENTATION
TO CLOSE OUT A REGULATORY GRANT

Transmittal Letter

SF 269 or SF 269A - Instructions for completing the form found in Chapter 5-60R.

OSM 51 - Instructions for completing the form found in Chapter 5-60R.

OSM 60 (Grant Acquired Property)

OSM 60 (Government Furnished Equipment)


Report of Government Property, Form OSM 60

Go to Forms page to download a copy of this form

INSTRUCTIONS FOR COMPLETING THE FORM OSM-60

Grant-Purchased Equipment. Recipients are required to account for equipment purchased with Federal funds for use under a specific grant program. Recipients may use the Form OSM-60, Report of Federal Property, or submit computer-generated records for this purpose. If computer-generated records are submitted, all items on the OSM-60 must be included.

Government-Furnished Property. Recipients are also required to account for all property provided by the Federal Government for use under a specific grant program. Recipients may use the Form OSM-60 for this purpose. Computer-generated records also may be used, as long as all items on the OSM-60 are included.

Detailed Instructions

Item 1, 3, 4 and 5: Self-explanatory.

Item 2: Enter the grant number.

Items 6(a), (b): Self-explanatory.

Items 6(c), (d): Enter the manufacturer's name and manufacturer's serial number for each item.

Item 6(e): Self-explanatory.

Item 6(f): Describe the present condition of the equipment being reported.

Item 6(g): List where each item of equipment is physically maintained.

Item 6(h): List the purchase price of the equipment, less credits and rebates.

Item 6(I): Enter the date purchased or received by the recipient.

Item 6(j): Enter the suggested disposition of each item of equipment.

Item 6(k), (l), and (m): If appropriate, OSM shall provide specific disposition instructions and return a copy ofForm OSM-60 to the recipient. If the recipient is not requesting to dispose of or trade-in the equipment, the equipment should be transferred to the next grant or cooperative agreement, and continue to be used to support the funded program.


EXHIBIT X5-70R-2

Grant and Cooperative Agreement closeout Checklist, Form OSM 61R

GRANT AND COOPERATIVE AGREEMENT CLOSEOUT CHECKLIST

STATE/TRIBE: GRANT NO.
Part A. Has the Recipient: Y N NA
1. Stated in the transmittal that it considers the grant to be complete, that payments from OSM for all allowable costs have been made, and that OSM is released from all obligations under or arising from the grant?      
2. Submitted the final performance report, OSM 51?      
3. Submitted the final financial status report, SF 269 or SF 269A?      
4. Submitted an inventory of federally-owned property, OSM 60, received under the grant?      
5. Submitted an inventory of grant-purchased property, OSM-60, requesting disposal or transfer to another grant?      
6. Reported program in accordance with the program income option in the grant award?      
Part B. Has the OSM Reviewing Office: Y N NA
1. Verified that all known changes have been incorporated into the grant by appropriate revisions or amendments?      
2. Notified other Federal agencies involved in the grant of closeout actions?      
3. Resolved all suspensions, withholdings, disputes and violations of grant clauses and assurances with the recipient?      
4. Prepared a brief written evaluation of the recipient's performance and placed a copy in the grant file?      
5. Approved the transfer or disposition of grant-purchased property to another grant?      
6. Reconciled the inventory of federally-owned property reported on the OSM-60 to OSM records, and approved the transfer to a subsequent grant?      
7. As appropriate, completed FAADS input.      
8. Prepared an OSM 52 to deobligate funds and/or close the grant?      

OSM 61R
Revised 8/97


GRANT AND COOPERATIVE AGREEMENT CLOSEOUT CHECKLIST - Continued

Part C. Closeout Documentation DATE
    SF 269/269A

OSM 51

OSM 60

OSM 60

OSM 52

OSM 61R

DI-1961

--

--

Final Financial Status Report

Performance Report

Grant-Purchased Equipment

Federally-Owned Equipment

Obligation Report

Closeout Checklist

FAADS Reporting Form

Evaluation Report (Monitoring Statement)

Other Documents (Explain)

 
Part D. Financial Information DATE
  Amount Awarded

Less Expenditures

Amount Deobligated

$                                                   

$                                                   

$                                                   

 


Financial information agrees with ABACIS               Y              N

OSM 52 completed and forwarded to DFM



                        
Prepared by                                                        
Date Prepared                                               

OSM 61R
Revised 8/97

FEDERAL ASSISTANCE MANUAL
January 2, 1998


(FAM Contents) (Definitions) (Acronyms) (Home Page)

Page Master: Marie Sibrell
Office of Surface Mining
1951 Constitution Ave. N.W.
Washington, D.C. 20240
202-208-2719
getinfo@osmre.gov